KP Energy Completes 16.8 MW Wind Power Project in Sidhpur

0
224

KP Energy Limited has commissioned 16.8 MW (Phase-VIII) inter state transmission system (ISTS) connected wind power project comprising eight numbers of wind turbine generators (WTGs) of 2.1 MW each at Sidhpur site in Devbhoomi Dwarka.

This Phase-VIII commissioning is a part of the 250.8MW ISTS connected wind power project capacity awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited under Tranche-VIII bidding. KP Energy is developing the project for Apraava Energy as a contractor under the land and balance of plant contract. With the present Phase-VIII commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 210 MW against the awarded capacity of 250.8 MW.

Previous articleMekong River Electrification Project Secures USD 120M Funding
Next articleReliance Power Subsidiaries Resolve Rs 10.23 Billion Debt