KP Energy commissions 25.2 MW ISTS-connected wind project in Sidhpur

0
468

KP Energy Limited has commissioned 25.2 MW (Phase-VI) inter state transmission system (ISTS) connected wind power project comprising 12 numbers of wind turbine genersators (WTGs) of 2.1 MW each at Sidhpur site in Devbhoomi Dwarka, Gujarat.

This Phase-VI commissioning is a part of the 250.8 MW ISTS connected wind power project capacity awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited under Tranche-VIII bidding. KP Energy is developing the project for Apraava Energy as a contractor under the land and balance of plant contract. With the present Phase-VI commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 163.8 MW against the awarded capacity of 250.8 MW.

Previous articleWorld Bank, Japan sign RISE deal for clean energy supply chain boost
Next articleSuzlon secures 30 MW order for 3 MW series from EDF Renewables

LEAVE A REPLY

Please enter your comment!
Please enter your name here