Latvenergo AS has purchased the 124 MW Telšiai project from Utilitas Wind. The project is expected to commence energy production in the first quarter of 2026. The construction of the wind farm will be managed by Utilitas Wind until completion.
Furthermore, installation of 20 Vestas 6.2 MW wind turbines is planned within the framework of the project. Upon completion, the Telšiai wind farm is expected to produce sufficient electricity to power over 125,000 households annually.
The construction of the connection, access roads, cabling, turbine foundations and assembly area will be done by Merko statyba UAB. Additionally, project management will be provided by Utilitas Wind. The estimated construction cost for the wind farm is approximately €200 million.